Churachandpur·
🏗️

Infrastructure

Last sourced: 14/09/2026

Data Transparency Notice:Infrastructure project data on this page is aggregated from NHIDCL (Ministry of Road Transport & Highways), AIIB project monitoring reports, CCML, Government of Manipur budget documents, Lok Sabha parliamentary records, and the Manipur project monitoring portal (darpanmanipur.in). Your Manipur does not independently verify construction progress or budget figures. Each data point is linked to its source. For official project status, contact the executing agency directly. This is not an official government tracker.

🛣️ National Highway Projects (NHIDCL)

✅ Completed: Widening to 2-lane with Hard shoulder of Churachandpur to Tuivai Section of NH 102B from km 0.000 to km 13.747 in the State of Manipur on EPC mode under NH(O) (Pkg- I A)

NHIDCL · Krishna Construction Co.nhidcl.com
✅ Completed · 15-05-2023📏 13.75 km · 💰 ₹151.32 Cr
🔗 View official source →

13.75 km · ₹151.32 Cr · Completed 15-05-2023. Contractor: Krishna Construction Co..

📋 Updated: 14 September 2026·

✅ Completed: Widening to 2-lane with Hard shoulder of Churachandpur to Tuivai Section of NH-102B from km32.835 to km48.587 in the State of Manipur on EPC mode under NH(O) (Pkg- IIA)

NHIDCL · Bharat Vanijya Eastern Pvt. Ltd.(BVEPL)nhidcl.com
✅ Completed · 28-03-2026📏 15.75 km · 💰 ₹232.99 Cr
🔗 View official source →

15.75 km · ₹232.99 Cr · Completed 28-03-2026. Contractor: Bharat Vanijya Eastern Pvt. Ltd.(BVEPL).

📋 Updated: 14 September 2026·

✅ Completed: Widening to 2-lane with Hard shoulder of Churachandpur to Tuivai Section of NH-102B from km13.747 to km32.835 in the State of Manipur on EPC mode under NH(O) (Pkg-1B)

NHIDCL · RSM Infra Projectsnhidcl.com
✅ Completed · 27-02-2026📏 19.09 km · 💰 ₹241.52 Cr
🔗 View official source →

19.09 km · ₹241.52 Cr · Completed 27-02-2026. Contractor: RSM Infra Projects.

📋 Updated: 14 September 2026·

Widening to 2-lane with Hard shoulder of Churachandpur to Tuivai Section from Km118.850 to km130.00 in the State of Manipur on EPC mode under NH(O) (Pkg-IVA) -(Balance Work)

NHIDCL · A K Shivhare Infrastructure Pvt. Ltd.nhidcl.com
🛣️ Ongoing · 📏 11.15 km · 💰 ₹204.12 Cr📊 Physical: 25% · Financial: 21%
🔗 View official source →

11.15 km · ₹204.12 Cr · 25% complete (financial: 21%). Started: 30-08-2025. Likely completion: 29-08-2026.

📋 Updated: 14 September 2026·

Widening to 2-lane with Hard shoulder of Churachandpur to Tuivai Section from Km 48.587 to Km 69.875 in the State of Manipur on EPC mode under NH(O) (Package-II B)

NHIDCL · Bharat Vanijya Eastern Pvt. Ltd.(BVEPL)nhidcl.com
🛣️ Ongoing · 📏 21.28 km · 💰 ₹365.53 Cr📊 Physical: 88% · Financial: 80%
🔗 View official source →

21.28 km · ₹365.53 Cr · 88% complete (financial: 80%). Started: 05-08-2020. Likely completion: 31-08-2026.

📋 Updated: 14 September 2026·

Strengthening of Churachandpur to Imphal section ol old NH-150 (new NH-02) from starting from Churachandpur Police Station (Km 402.000) to Malom oil Depot Gate (km 454.798) in Manipur on EPC mode under NH(O)-NE (Length=53.400Km)

NHIDCL · Jay Shree Internationalnhidcl.com
🛣️ Ongoing · 📏 53.40 km · 💰 ₹76.09 Cr📊 Physical: 6% · Financial: 0%
🔗 View official source →

53.40 km · ₹76.09 Cr · 6% complete (financial: 0%). Started: 03-10-2025. Likely completion: 02-10-2026.

📋 Updated: 14 September 2026·

Balance work of Widening to 2 (Two) lane with hard shoulder of Churachandpur to Tuivai section of NH-102B from km 130.000 to km 141.029 (Package-4B) in the State of Manipur on EPC Mode

NHIDCL · A K Shivhare Infrastructure Pvt. Ltd.nhidcl.com
🛣️ Ongoing · 📏 11.03 km · 💰 ₹177.76 Cr📊 Physical: 7% · Financial: 4%
🔗 View official source →

11.03 km · ₹177.76 Cr · 7% complete (financial: 4%). Started: 08-11-2025. Likely completion: 07-11-2026.

📋 Updated: 14 September 2026·

Widening to 2-lane with Hard shoulder of Churachandpur to Tuivai Section of NH-102B from Design Chainage 69.875 Km to 121.769 Km in the State of Manipur on EPC mode (Package-3)

NHIDCL · M & S Co.nhidcl.com
🛣️ Ongoing · 📏 51.89 km · 💰 ₹673.27 Cr📊 Physical: 85% · Financial: 84%
🔗 View official source →

51.89 km · ₹673.27 Cr · 85% complete (financial: 84%). Started: 25-08-2021. Likely completion: 31-12-2026.

📋 Updated: 14 September 2026·

NHIDCL Highway Projects — Churachandpur

NHIDCL · MoRTH, GoInhidcl.com
5 ongoing · 3 completed · ₹2123 Cr invested📊 Average progress: 42% · Source: NHIDCL PMIS (live data)
🔗 View official source →

8 NHIDCL projects in Churachandpur: 5 ongoing, 3 completed, 0 upcoming. Total investment: ₹2123 Cr. Average progress: 42%.

📋 Updated: 14 September 2026·

🏙️ Urban Infrastructure & Major Projects

National Highway Development — Manipur (Parliamentary Report)

NHIDCL · MoRTH · PWD ManipurLok Sabha (MoRTH)
📊 754 km completed · 🚧 325 km under execution · 📋 51 NHIDCL packages · 181 km PWD (5-year)Verified source: Lok Sabha Unstarred Q No. 805, answered 4 Dec 2025 by MoRTH. Full PDF with project-wise annexure available.
🔗 View official source →

Manipur has 1,692 km of national highways — 1,399 km under NHIDCL, 293 km under State PWD (routine maintenance only). As of Dec 2025: 51 works covering 1,079 km taken up by NHIDCL; 754 km completed, 325 km remaining under execution. State PWD blacktopped 181 km in the last 5 years. NH-137A strengthening sanctioned 21 Oct 2025 at ₹74.22 Cr. Annexure with project-wise completion dates included in the parliamentary reply.

📋 Updated: 14 September 2026·

Source: darpanmanipur.in · PMGSY · NHIDCL · AIIB · News reports · NDSAP