Data Transparency Notice:Infrastructure project data on this page is aggregated from NHIDCL (Ministry of Road Transport & Highways), AIIB project monitoring reports, CCML, Government of Manipur budget documents, Lok Sabha parliamentary records, and the Manipur project monitoring portal (darpanmanipur.in). Your Manipur does not independently verify construction progress or budget figures. Each data point is linked to its source. For official project status, contact the executing agency directly. This is not an official government tracker.

🛣️ National Highway Projects (NHIDCL)

✅ Completed: Improvement of existing road to 2 laning with Hard Shoulders of Maram-Peren section (Package-2A, length- 16.840 Km) from Design Chainage 40.000 km to 56.840 km on NH-129A in the State of Manipur on EPC mode

NHIDCL · Heera Ram Godara - Dudi & Company (JV)nhidcl.com
✅ Completed · 12-02-2023📏 16.84 km · 💰 ₹204.58 Cr
🔗 View official source →

16.84 km · ₹204.58 Cr · Completed 12-02-2023. Contractor: Heera Ram Godara - Dudi & Company (JV).

📋 Updated: 14 September 2026·

✅ Completed: Improvement of existing road to 2 lanning with Hard Shoulders of Maram Peren section (Package-III, length - 34.494 km) from Design Chainage km 75+000 to 109+494 km on NH-129A in the State of Manipur on EPC mode under NH(O)-TSP

NHIDCL · New India Contractors & Developers Pvt. Ltd. - Bharat Construction Co. (JV)nhidcl.com
✅ Completed · 28-02-2025📏 34.49 km · 💰 ₹467.41 Cr
🔗 View official source →

34.49 km · ₹467.41 Cr · Completed 28-02-2025. Contractor: New India Contractors & Developers Pvt. Ltd. - Bharat Construction Co. (JV).

📋 Updated: 14 September 2026·

✅ Completed: Improvement of existing road to 2 laning with Hard Shoulders of Maram-Peren section (Package-1B, length- 17.660 km) from Design Chainage 22.340 km to 40.000 km on NH-129A in the State of Manipur on EPC mode

NHIDCL · CSR Infratech India Pvt. Ltd.- Raam Infratech India Pvt. Ltd. (JV)nhidcl.com
✅ Completed · 06-03-2026📏 17.66 km · 💰 ₹188.36 Cr
🔗 View official source →

17.66 km · ₹188.36 Cr · Completed 06-03-2026. Contractor: CSR Infratech India Pvt. Ltd.- Raam Infratech India Pvt. Ltd. (JV).

📋 Updated: 14 September 2026·

✅ Completed: Improvement of existing road to 2 laning with Hard Shoulders of Maram-Peren section (Package-2B, length- 18.160 Km) from Design Chainage 56.840 km to km 75.000 on NH-129A in the State of Manipur on EPC mode

NHIDCL · Satya Buildersnhidcl.com
✅ Completed · 12-01-2024📏 18.16 km · 💰 ₹232.63 Cr
🔗 View official source →

18.16 km · ₹232.63 Cr · Completed 12-01-2024. Contractor: Satya Builders.

📋 Updated: 14 September 2026·

NHIDCL Highway Projects — Senapati

NHIDCL · MoRTH, GoInhidcl.com
4 completed · ₹1093 Cr invested✅ All projects completed
🔗 View official source →

4 NHIDCL projects in Senapati: 0 ongoing, 4 completed, 0 upcoming. Total investment: ₹1093 Cr.

📋 Updated: 14 September 2026·

🏙️ Urban Infrastructure & Major Projects

National Highway Development — Manipur (Parliamentary Report)

NHIDCL · MoRTH · PWD ManipurLok Sabha (MoRTH)
📊 754 km completed · 🚧 325 km under execution · 📋 51 NHIDCL packages · 181 km PWD (5-year)Verified source: Lok Sabha Unstarred Q No. 805, answered 4 Dec 2025 by MoRTH. Full PDF with project-wise annexure available.
🔗 View official source →

Manipur has 1,692 km of national highways — 1,399 km under NHIDCL, 293 km under State PWD (routine maintenance only). As of Dec 2025: 51 works covering 1,079 km taken up by NHIDCL; 754 km completed, 325 km remaining under execution. State PWD blacktopped 181 km in the last 5 years. NH-137A strengthening sanctioned 21 Oct 2025 at ₹74.22 Cr. Annexure with project-wise completion dates included in the parliamentary reply.

📋 Updated: 14 September 2026·

Source: darpanmanipur.in · PMGSY · NHIDCL · AIIB · News reports · NDSAP

Last sourced: 14/09/2026