Data Transparency Notice:Infrastructure project data on this page is aggregated from NHIDCL (Ministry of Road Transport & Highways), AIIB project monitoring reports, CCML, Government of Manipur budget documents, Lok Sabha parliamentary records, and the Manipur project monitoring portal (darpanmanipur.in). Your Manipur does not independently verify construction progress or budget figures. Each data point is linked to its source. For official project status, contact the executing agency directly. This is not an official government tracker.

🛣️ National Highway Projects (NHIDCL)

✅ Completed: Widening to 2 -Lane with Paved shoulder of Imphal to Jiribam section of NH-37 from Design Chainage 33.000 km to 66.390 Km (Existing Chainage from km 33.395 to km 67.496) on EPC Mode in Manipur (PKG-3)

NHIDCL · Mehta Construction Co. - Ganpati Builders (JV)nhidcl.com
✅ Completed · 01-02-2026📏 33.16 km · 💰 ₹467.00 Cr
🔗 View official source →

33.16 km · ₹467.00 Cr · Completed 01-02-2026. Contractor: Mehta Construction Co. - Ganpati Builders (JV).

📋 Updated: 14 September 2026·

✅ Completed: Construction of 4-Lane Bridge over Irang River on Imphal-Jiribam road section (at 95.50 Km) on NH-53 (New NH-37) on EPC mode in Manipur

NHIDCL · Paratech Constructions Pvt. Ltd.nhidcl.com
✅ Completed · 27-12-2024📏 0.13 km · 💰 ₹49.31 Cr
🔗 View official source →

0.13 km · ₹49.31 Cr · Completed 27-12-2024. Contractor: Paratech Constructions Pvt. Ltd..

📋 Updated: 14 September 2026·

Widening to 2 -Lane with Paved shoulder of Imphal to Jiribam section of NH-37 from Design Chainage 66.110 km to 101.280 Km (Existing Chainage km 67.496 to km 103.557) on EPC Mode in Manipur (PKG-4)

NHIDCL · BLA Projects Private Limited - G P Projects Ltd. (JV)nhidcl.com
🛣️ Ongoing · 📏 35.17 km · 💰 ₹579.63 Cr📊 Physical: 86% · Financial: 83%
🔗 View official source →

35.17 km · ₹579.63 Cr · 86% complete (financial: 83%). Started: 27-06-2022. Likely completion: TBD.

📋 Updated: 14 September 2026·

Widening to 2-Lane with Paved shoulder of Imphal to Jiribam section of NH-37 from Design Chainage 15.940 km to 33.120 Km (Existing Chainage Km 15.946 to Km 33.395) (Total length=17.180 Km) in the State of Manipur on (EPC) mode (PKG-2) - Balance Works & Rectification works

NHIDCL · SCONS Infrastructure Pvt. Ltd.nhidcl.com
🛣️ Ongoing · 📏 17.18 km · 💰 ₹195.14 Cr📊 Physical: 93% · Financial: 91%
🔗 View official source →

17.18 km · ₹195.14 Cr · 93% complete (financial: 91%). Started: 18-03-2025. Likely completion: 03-08-2026.

📋 Updated: 14 September 2026·

Widening to 2 Lane with Paved shoulder of lmphal to Jiribam section of NH-37 from Design Ch. from km 131.280 to km 169.570 on EPC mode in Manipur under NH(O)-TSP (PKG-6)

NHIDCL · Sarjan Infracon Pvt. Ltd.nhidcl.com
🛣️ Ongoing · 📏 38.29 km · 💰 ₹504.76 Cr📊 Physical: 95% · Financial: 93%
🔗 View official source →

38.29 km · ₹504.76 Cr · 95% complete (financial: 93%). Started: 07-02-2023. Likely completion: 16-09-2026.

📋 Updated: 14 September 2026·

NHIDCL Highway Projects — Jiribam

NHIDCL · MoRTH, GoInhidcl.com
3 ongoing · 2 completed · ₹1796 Cr invested📊 Average progress: 91% · Source: NHIDCL PMIS (live data)
🔗 View official source →

5 NHIDCL projects in Jiribam: 3 ongoing, 2 completed, 0 upcoming. Total investment: ₹1796 Cr. Average progress: 91%.

📋 Updated: 14 September 2026·

🏙️ Urban Infrastructure & Major Projects

National Highway Development — Manipur (Parliamentary Report)

NHIDCL · MoRTH · PWD ManipurLok Sabha (MoRTH)
📊 754 km completed · 🚧 325 km under execution · 📋 51 NHIDCL packages · 181 km PWD (5-year)Verified source: Lok Sabha Unstarred Q No. 805, answered 4 Dec 2025 by MoRTH. Full PDF with project-wise annexure available.
🔗 View official source →

Manipur has 1,692 km of national highways — 1,399 km under NHIDCL, 293 km under State PWD (routine maintenance only). As of Dec 2025: 51 works covering 1,079 km taken up by NHIDCL; 754 km completed, 325 km remaining under execution. State PWD blacktopped 181 km in the last 5 years. NH-137A strengthening sanctioned 21 Oct 2025 at ₹74.22 Cr. Annexure with project-wise completion dates included in the parliamentary reply.

📋 Updated: 14 September 2026·

Source: darpanmanipur.in · PMGSY · NHIDCL · AIIB · News reports · NDSAP